• Main Office: 01442 216785 | email: Info@mtshealth.co.uk
    Harlow Service Centre: 01279 976017

Barts Health NHS Trust Royal London Hospital

queen-news-8

Equipment Procurement Managers

MTS Health has been working with the Trust for nearly 14 years.

This project involved the planning, specifying, procuring, installing and commissioning of all the non-medical equipment (£10m). The project is the largest PFI in Europe and involved 3 tower blocks of over 14 storeys each; with a total of 10,000 rooms to be equipped.

MTS completed this project on time and under budget, and it was opened by the Queen in 2012.

Catherine Holmes, Senior Project Manager of MTS had at times, up to four team members co-ordinating the procurement, logistics and installation of the furniture and equipment. This was a joint collaboration with the Trust Capital team.